IREB Construction Interruptions

IREB Construction Interruptions

Phase 1 – Modifications to Existing Sanitary Sewer
– 10/14 – 11/18 ? West side of Clifton St. will be closed down to complete sanitary sewer modifications.
– Entrances into PCC Lot 1, Parking Garage 4, Loading Dock for RES, and EAD Lot 6 will remain in service during utility work. (utility plates to be installed as required)
– Clifton St. will be one lane during Phase 1 with traffic being able to travel north.
– Detour signage will be set in place to guide traffic south either down Boland St. or Montgomery St. to Camp Bowie Blvd. to access Clifton St. from the south.
Phase 2 – Modifications to Existing Water Service
– 11/18 ? 12/19 ? East side of Clifton St. will be closed down to complete water line services upgrades.
– Entrances into Lot 2 and Parking Garage 5 will remain in service during utility work. (utility plates to be installed as required)
– Clifton St. will be one lane during Phase 2 with traffic being able to travel south.
– Detour signage will be set in place to guide traffic north either up Boland St. or Montgomery St. to Camp Bowie Blvd. to access Clifton St. from the north.